Time Lapse – Roving – 1st Storey Building Envelope Installation

A series of time lapse videos recording the construction of a single family dwelling in North Vancouver BC Canada.

This video records activities from Aug 26 to October 7, 2017 covering the following:

– Continued installation of Delta Vent SA sheathing membrane
– Continued installation of 6″ of ROXUL ComfortBoard 80 continuous exterior insulation
– Installing window sill flashings
– Installing cedar beams to support south elevation 1st storey sun shades
– Installing Coulson engineered horizontal T&G cedar siding

Visit us at http://www.theenclosure.ca/2017/10 for all the play by play excitement.